Creates an "End to Start" link between two tasks displayed in a Gantt Chart column found in a Table (or TreeView Table) control.
Example
// Create the tasks then the link
t1 is GanttTask
t1..ID = "T1"
t2 is GanttTask
t2..ID = "T2"
GanttAddLink(COL_Gantt, t1..ID, t2..ID)

// Other syntax by specifying the type of link
GanttAddLink(COL_Gantt, t1..ID, t2..ID, gltEndToStart)
// Create a link via a GanttLink variable
Link is GanttLink
Link..SourceID = "T1"
Link..DestinationID = "T2"
Link..Type = gltEndToStart
GanttAddLink(COL_Gantt, Link)
Syntax

Creating a link between two existing tasks Hide the details

GanttAddLink(<Gantt Column> , <Identifier of Source Task> , <Identifier of Destination Task> [, <Type of Link>])
<Gantt Column>: Character string (with or without quotes)
Name of the Gantt Chart column (found in a Table or TreeView Table control) to use.
<Identifier of Source Task>: Character string (with quotes)
Identifier of the source task of the link.
<Identifier of Destination Task>: Character string (with quotes)
Identifier of the destination task of the link.
<Type of Link>: Integer constant
Type of link to add:
gltStartToStart"Start to Start" link: The destination task cannot start as long as the source task is not started.
gltStartToEnd"Start to End" link: The destination task cannot end as long as the source task is not started (rare case).
gltEndToStart
(default value)
"End to Start" link: The destination task cannot start as long as the source task is not ended.
gltEndToEnd"End to End" link: The destination task cannot end as long as the source task is not ended.
This parameter is available from version 190044. In the earlier versions, the created link will automatically be an "End to Start" link.

Creating a link via a GanttLink variable Hide the details

GanttAddLink(<Link>)
<Link>: GanttLink variable
Name of the GanttLink variable describing the link to create.
Remarks
  • The function has no effect if the link already exists.
  • If one of the identifiers does not exist, the link is inactive: the link is not displayed and it has no effect.
  • According to their types, the links are drawn on the start or end borders of the tasks.
Related Examples:
The Gantt control Unit examples (WINDEV): The Gantt control
[ + ] Using a Gantt Chart control
WD Gantt Complete examples (WINDEV): WD Gantt
[ + ] The "WD Gantt" example presents an advanced use of the Gantt Chart control.
This example is used to create a Gantt chart with tasks, links, cumulative tasks and milestones.
The tasks can be edited in a specific window.
The created chart can be saved in a file and reloaded thereafter.